- Main Contractor : ETA PPD
- Client Name : DEWA
- Job Order No : JO/001
- Year : 2008
- Region : Ras Al Khor
- Project Description:
- Design Engineering works
- Main Contractor : Centaur E.M.Co. L.L.C.
- Client Name : DEWA
- Job Order No : JO/002
- Year : 2008
- Region : Jebel Ali
- Project Description:
- Design & Supervision of ERS BP
- Main Contractor : Areva T & D
- Client Name : FEWA (UAE)
- Job Order No : JO/003
- Year : 2008
- Region : Dhaid
- Project Description:
- Assembly &Installation of 400kV Gantries and other structures
- Main Contractor : Areva T & D
- Client Name : DEWA
- Job Order No : JO/004
- Year : 2008
- Region : Abu Dhabi
- Project Description:
- Project Coordination
- Main Contractor : Remcon Electrical Co. (L.L.C.)
- Client Name : TRANSCO
- Job Order No : JO/005
- Year : 2008
- Region : Mafraq
- Project Description:
- Design/supply of OH Gantry
- Main Contractor : Centaur E.M.Co. L.L.C.
- Client Name : DEWA
- Job Order No : JO/006
- Year : 2008
- Region : Al Quoz
- Project Description:
- Design Enquiry and supervision
- Main Contractor : Areva T & D
- Client Name : DEWA
- Job Order No : JO/007
- Year : 2008
- Region : JAFZA Substation
- Project Description:
- Tie in works at 400 kV Substation
- Main Contractor : Hyundai Engineering & Construction Co. (L.L.C.)
- Client Name : DEWA
- Job Order No : JO/008
- Year : 2008
- Region : Jebel Ali
- Project Description:
- Erection of Gantry Towers and Substation
- Main Contractor : Emirates Trade Agency (ETA)
- Client Name : TRANSCO
- Job Order No : JO/009
- Year : 2008
- Region : Shuweihat S/S to Sila Grid Station
- Project Description:
- Transco Tender No. N-6693
- Main Contractor : Zamil Steel Industries-L.L.C
- Client Name : Zamil Steel
- Job Order No : JO/010
- Year : 2008
- Region : Ras Al Khaimah
- Project Description:
- Tower proto Assembly
- Main Contractor : Centaur E.M.Co. L.L.C.
- Client Name : RTA
- Job Order No : JO/011
- Year : 2008
- Region : Nad Al Sheba
- Project Description:
- Stage 2A Nad Al Sheba Race course development
- Main Contractor : ETA Star International LLC
- Client Name : TRANSCO
- Job Order No : JO/012
- Year : 2008
- Region : Al Ain
- Project Description:
- Design Engineering for conversion
- Main Contractor : Areva T & D
- Client Name : FEWA
- Job Order No : JO/013
- Year : 2009
- Region : Dhaid
- Project Description:
- 220kV Cable Installation works at GIS 400/220kv substation Basement.
- Main Contractor : Hyundai Engineering & Construction Co. (L.L.C.)
- Client Name : DEWA
- Job Order No : JO/014
- Year : 2009
- Region : Jebel Ali
- Project Description:
- Gantry Erection works at L S/S
- Main Contractor : Areva T & D
- Client Name : DEWA
- Job Order No : JO/015
- Year : 2009
- Region : Dhaid
- Project Description:
- Overhead line tie to substation
- Main Contractor : Kalpataru
- Client Name : Dept. of Transport Abu Dhabi
- Job Order No : JO/016
- Year : 2009
- Region : Al Ain South West to Umm Al Qush
- Project Description:
- Stringing of 60 kms 220kV DC OHL.
- Main Contractor : Cegelec
- Client Name : Total E & P
- Job Order No : JO/017
- Year : 2009
- Region : Yemen
- Project Description:
- TEPY Overhead Line Project
- Main Contractor : KEC International Limited
- Client Name : Dept. of Transport - Abu Dhabi
- Job Order No : JO/018
- Year : 2009
- Region : Ruwais By Pass
- Project Description:
- Modification & relocation works
- Main Contractor : Areva T & D
- Client Name : DEWA
- Job Order No : JO/019
- Year : 2010
- Region : Barsha S/S
- Project Description:
- 400 kV GANTRY INSTALLATION at 'M' Station,Jebel Ali
- Main Contractor : Larsen & Toubro Limited
- Client Name : TRANSCO
- Job Order No : JO/020
- Year : 2010
- Region : Shamkha
- Project Description:
- Slack span stringing and jumpering
- Main Contractor : Areva T & D
- Client Name : DEWA
- Job Order No : JO/021
- Year : 2010
- Region : Horse Race S/s
- Project Description:
- Gantries Erection and Equipment
- Main Contractor : KEC International Limited
- Client Name : Dept. of Transport - Abu Dhabi
- Job Order No : JO/022
- Year : 2010
- Region : Ruwais By Pass
- Project Description:
- Modification & relocation works for OHL
- Main Contractor : Inabensa
- Client Name : FEWA
- Job Order No : JO/023
- Year : 2010
- Region : Fujairah - Dibba / Fujairah - Tayween
- Project Description:
- Generating ground profiles drawing based
- Main Contractor : Emirates Heavy Engineering
- Client Name : RAKIA
- Job Order No : JO/024
- Year : 2010
- Region : Al Ghail - Al Hamra
- Project Description:
- Complete Engineering & Supervision
- Main Contractor : ETA PPD
- Client Name : DEWA
- Job Order No : JO/025
- Year : 2010
- Region : Awir - Hatta
- Project Description:
- Verification of strength of 132kv
- Main Contractor : Gulf Jyothi
- Client Name : DEWA
- Job Order No : JO/026
- Year : 2011
- Region : L Station And G Station (DXB)
- Project Description:
- Theoretical calculation
- Main Contractor : HAWK International & TOTAL
- Client Name : Total E & P
- Job Order No : JO/027
- Year : 2011
- Region : Yemen
- Project Description:
- Detailed Engineering Services
- Main Contractor : Gulf Jyothi
- Client Name : DEWA
- Job Order No : JO/028
- Year : 2011
- Region : H Mushriff - G Mushriff (DXB)
- Project Description:
- Theoritical Calculation
- Main Contractor : Gulf Jyothi
- Client Name : DEWA
- Job Order No : JO/031
- Year : 2013
- Region : H Mushriff - G Mushriff (DXB)
- Project Description:
- Theoritical Calculations